Milestone Reached at La Salle College High School

LaSalleJan27

E. Allen Reeves, Inc. continues to make progress on the renovation & expansion of LaSalle College High School’s Glaser Center. Our team has completed the complex shoring & underpinning required for the new 5,000 sq ft. addition, which was crucial for keeping the project on schedule. The final steel supports are being set and roofing is underway. All work is being done while the school remains active and occupied, requiring careful coordination and close communication with school administration. Besides the new addition, over 11,000 sq ft. of interior space (primarily the cafeteria, kitchen, and server) will be completely transformed. The project, designed by Stantec, will be completed later this year.

Read more about this project here.